The Enugu Electricity Distribution Company PLC (EEDC) wishes to inform her esteemed customers in parts of Anambra State that the fault from the Transmission Company of Nigeria (TCN) Awada Station, which is the reason for the power outage being experienced for some days now is receiving attention.
Currently, the TCN engineers are transferring our 3-3, Obosi, and Ossamala 33KV feeders from the faulty TR11, 60MVA 132/33KV power transformer, to the newly commissioned 100MVA power transfomer in Awada TCN Station.
Also, in order to create a safe working space for the engineers, the TR13 60MVA and Mobitra 40MVA 132/33KV power transformers are switched off, thereby affecting Niccus, Nnewi-Oba, Nnewi Industrial, Awada 2 and Army Barracks 33KV feeders.
All customers that receive electricity supply from these feeders are currently out of supply.
We regret the inconveniences this development has caused our esteemed customers and assure them that once the maintenance is completed, supply will be restored.
We remain committed to providing improved service delivery.